When you buy machinery from China, the factory acceptance test (FAT) is the last and best opportunity to confirm that the equipment works as agreed before it leaves the supplier. Once a machine is crated and shipped, fixing problems becomes slow and expensive. Yet many buyers treat the FAT as a quick demonstration rather than a structured test. This guide explains how to plan and run a factory acceptance test for machinery purchased from China.
What is a factory acceptance test?
A factory acceptance test is a documented test of a machine or production line at the manufacturer’s facility, carried out against criteria agreed in advance. It confirms that the equipment matches the contract specification, performs to the agreed standard and is complete and ready for shipment. A FAT is different from a general pre-shipment inspection: it focuses on how the machine performs, not only on how it looks and what is in the crate.
1. Define acceptance criteria in the contract
The most common FAT problem is vague expectations. Before production starts, attach a technical specification and acceptance criteria to the purchase contract, for example:
- Output or cycle time with a defined product and material.
- Accuracy, tolerance or quality targets and how they will be measured.
- Duration of the test run, such as continuous running for a set number of hours.
- Acceptable reject or downtime rates.
- Safety functions to be demonstrated.
- Documentation that must be provided.
Also agree what happens if the machine fails: the supplier corrects the issues and repeats the test at its own cost before the balance payment is due.
2. Prepare a FAT protocol
A FAT protocol is a checklist that both parties agree before the test. It typically includes:
- Identification: model, serial number and photos of nameplates.
- Configuration check: components, brands and options compared with the contract.
- Mechanical checks: build quality, welding, alignment, guarding and finish.
- Electrical checks: voltage, wiring standard, cabinet layout, labelling and grounding.
- Functional tests: every axis, motion, station and mode of operation.
- Performance tests: output, accuracy and quality with your product or material.
- Safety tests: emergency stops, interlocks, light curtains and guards.
- Documentation review: manuals, electrical drawings, software backups, certificates and spare parts lists.
3. Provide materials and samples in time
Many machines can only be tested properly with the buyer’s product: packaging film and products for a packaging line, molds and resin for an injection molding machine, sheet metal for a press brake, or parts for a robot cell. Plan early who supplies the test materials and make sure they arrive at the factory before the scheduled FAT.
4. Who should attend?
Ideally, someone with technical knowledge of the machine and your process witnesses the FAT. If your team cannot travel to China, a local sourcing agent or inspection engineer can attend on your behalf, follow the agreed protocol and send photos, videos and measurements. Some buyers also join part of the test by live video so they can ask the supplier questions directly.
5. During the test
- Follow the protocol step by step and record results for each item.
- Run the machine long enough to reveal problems that do not appear in a short demonstration, such as overheating, leaks or drifting accuracy.
- Keep samples produced during the test, label them and, if needed, ship them to you for evaluation.
- Record videos of key functions and of the complete running cycle.
- List all open issues with clear responsibilities and deadlines.
6. After the FAT
A FAT report should summarise the results, open issues and the decision: accepted, accepted with conditions or rejected. Only release the balance payment once the agreed criteria are met or the remaining issues have been resolved. Then check packing, rust protection and loading, which are often handled in a separate pre-shipment inspection.
FAT vs SAT
A site acceptance test (SAT) is carried out after installation at your facility. The FAT reduces risk before shipment; the SAT confirms that the machine works in your real environment with your utilities and operators. For complex equipment, plan both.
Frequently asked questions
Will Chinese suppliers agree to a FAT?
Serious machinery manufacturers routinely run acceptance tests for export customers. If a supplier refuses any form of witnessed test, treat it as a warning sign.
Who pays for the FAT?
The supplier normally provides the test facility, labour and utilities. Buyers usually cover their own travel or inspection costs and the materials they supply. Agree this in the contract.
Can a FAT be done remotely?
A remote FAT by live video is better than none, but having a qualified person on site gives far more reliable results.
A structured FAT is especially important for complete production lines. We apply it in every food processing machinery sourcing in China project and in China automation equipment sourcing projects such as robot cells and automated assembly lines.
Let Supbon Sourcing witness your FAT
Supbon Sourcing is based in China and specialises in machinery. We help buyers write acceptance criteria, attend factory acceptance tests on their behalf, report results with photos and videos, and follow up open issues until shipment. Learn more about how we verify suppliers, how we ship machinery and how our fees work.
Have a machine nearly ready in China? Contact us to arrange a factory acceptance test.