Chinese New Year 2027: When to Order Machinery from China

Red and gold Chinese New Year lanterns

Chinese New Year is the biggest interruption in the Chinese manufacturing calendar, and in 2027 it falls on February 6. The official public holiday lasts about a week, but its real effect on machinery orders is much longer. Factories slow down before it, close for it, and take time to return to normal after it. If you are planning to buy machinery from China in the coming months, now is the time to work backwards from that date.

1. How the holiday affects machinery orders

  • Before the holiday: factories rush to finish orders. Schedules fill up, and suppliers may be less willing to accept new orders with tight delivery dates. Rushed work is also a quality risk.
  • During the holiday: many factories close for longer than the official holiday, often for two weeks or more, and component suppliers close too.
  • After the holiday: factories may take several weeks to get back to full output, as some workers return late or change jobs. New workers need training.
  • Logistics: trucking, port and forwarder capacity can get tight in the weeks before the holiday, and freight rates may rise.

2. Work backwards from the holiday

The exact timing depends on your machine and supplier, but here is how to think about it:

  • Allow for the lead time, which is often 30 to 60 days or more for machines. Complex lines take longer.
  • Add time for testing, any corrections, inspection, packing and loading.
  • Aim to have the machine ready and loaded well before factories wind down, which often begins in mid to late January.
  • For many standard machines, that means placing the order and paying the deposit by about late November or early December 2026. For complex or custom machines, it may already be too late to ship before the holiday, so confirm dates with your supplier.

3. If you cannot ship before the holiday

Sometimes it is better to accept a later date than to rush. Agree a realistic delivery date after the holiday, and leave room for the slow restart. Plan it into your project schedule and tell your customers early. Many machines ordered in January will not realistically ship until March or later.

4. Protect quality during the rush

5. Payments and shipping

  • Allow for banks being closed during the holiday, and do not leave payments until the last moment.
  • Be alert to fake “new bank account” emails, which can appear at busy times. See payment terms and scams.
  • Book freight early and confirm loading dates with your forwarder. See shipping machinery from China.
  • Make sure documents are ready before staff leave. See customs documents.

6. Other holidays to watch

National Day in early October and Labour Day in early May also affect factories and logistics, though less severely. Build them into long projects. Exact holiday dates are announced by the government each year.

Frequently asked questions

How long do factories actually close?

It varies. Many close for about two weeks or more, and some close longer. Ask each supplier for its exact closing and reopening dates.

Can I visit factories around the holiday?

Avoid the weeks around it. Staff are busy before the holiday, factories are shut during it and production is slow afterwards. See planning a factory visit.

Can you keep an eye on our order during the rush?

Yes. A local agent can follow production, confirm real progress and inspect before shipment.

Plan your order with Supbon Sourcing

Supbon Sourcing is based in Jinan. We help buyers plan realistic schedules, follow production, inspect machines and coordinate shipping around the holidays. Learn more about our machinery sourcing service.